CAPS Fiscal Year End 2013 Deadlines

To ensure that all necessary approvals are in place and all accounting entries are completed in time, appropriate CAPS forms must be submitted to Central Administration by your School/Unit's Authorized Requestor through the CAPS automated system by the dates set forth below.

  • Friday, May 10th - Completed Project Proposals (PPs) and Construction Authorizations (CAs)
  • Monday, June 10th (12 p.m.) - Completed Construction Close Requests (CCRs)

Forms submitted by the specified dates will be processed in FY2013; forms submitted after the deadline will be held in a queue and processed in FY2014 when the CAPS system re-opens for approval on Monday, July 1, 2013.

Tag; Fiscal Year End, CAPS

Email | Top